Connect with us

Economy

Power Generation Returns to 4,000MW as Hydro Plants Recover

Published

on

Power - Investors King
  • Power Generation Returns to 4,000MW as Hydro Plants Recover

The nation’s power generation has returned to the 4,000 megawatts mark following the recovery in the output of hydropower plants and a few thermal plants.

The nation generates most of its electricity from gas-fired power plants, while output from hydropower plants makes up about 30 per cent of total generation.

Generation from Kainji, Jebba and Shiroro hydro plants fell to 173MW, 210MW and 205MW, respectively as of 6am on November 25 from 403MW, 340MW and 295 on November 23.

The total generation, therefore, dropped from 4,077.8MW on November 23 to 3,662.6MW on November 25, according to the latest data obtained from the Federal Ministry of Power, Works and Housing on Thursday.

But the generation rose to 4,016.1MW on November 28 from the 3,828.2MW recorded the previous day, buoyed largely by the increase in the output from Kainji, Jebba and Shiroro hydro plants, which generated 382MW, 326MW and 199MW, respectively that day.

Electricity generation from Egbin, the nation’s biggest power station, stood at 513MW on November 28, compared to the 1,085MW achieved on March 15, 2016. The plant has an installed capacity of 1,320MW, consisting of six units of 220MW each.

Six power plants, including Sapele I and Alaoji II, were not generating any megawatt as of 6am on November 28.

Other idle plants were Gbarain II, AES, ASCO and Rivers IPP, according to the ministry.

Sapele’s ST1 unit was said to have tripped on low drum level; the ST2 out on maintenance; the ST4 and 5 awaiting major overhaul; and the ST6 tripped on gas control valve not following reference point.

Units GT1 and 2 of Alaoji tripped due to low gas pressure; the GT3 was shut down due to generator air inlet filter trouble, and the GT4 out on maintenance.

Gbarain’s GT2 unit was out due to heater problem; the AES, out of production since November 27, 2014; ASCO’s GT1 was shut down due to leakage in the furnace, and the Rivers IPP, out of production since November 16, 2016.

The nation’s power grid has suffered 24 collapses, 15 of which are total and nine, partial, so far this year.

Unutilised generation capacity stood at 2,281MW due to gas constraint (810MW), line constraints (234MW), frequency management occasioned by the electricity generation companies’ load demand (1,287MW) and water management (150MW).

In October, the Managing Director/Chief Executive Officer, Niger Delta Power Holding Company, Mr. Chiedu Ugbo, said the power plants built under the National Integrated Power Project scheme had suffered from load rejection by the Discos.

Meanwhile, the Executive Director, Research and Advocacy of the Association of Nigerian Electricity Distributors, Mr. Sunday Oduntan, said last month that the capacity of the distribution network had increased to 6,200MW.

Is the CEO/Founder of Investors King Limited. A proven foreign exchange research analyst and a published author on Yahoo Finance, Businessinsider, Nasdaq, Entrepreneur.com, Investorplace, and many more. He has over two decades of experience in global financial markets.

Continue Reading
Comments

Economy

Nigeria’s Cash Transfer Scheme Shows Little Impact on Household Consumption, Says World Bank

Published

on

world bank - Investors King

The World Bank has said Nigeria’s conditional cash transfer scheme aimed at bolstering household consumption and financial inclusion is largely ineffective.

Despite significant investment and efforts by the Nigerian government, the program has shown minimal impact on the lives of its beneficiaries.

Launched in collaboration with the World Bank in 2016, the cash transfer initiative was designed to provide financial support to vulnerable Nigerians as part of the National Social Safety Nets Project.

However, the latest findings suggest that the program has fallen short of its intended goals.

The World Bank’s research revealed that the cash transfer scheme had little effect on household consumption, financial inclusion, or employment among beneficiaries.

Also, the program’s impact on women’s employment was noted to be minimal, highlighting systemic challenges in achieving gender parity in economic opportunities.

Despite funding a significant portion of the cash transfer program, the World Bank found no statistical evidence to support claims of improved financial inclusion or household consumption.

The report underscored the need for complementary interventions to generate sustainable improvements in households’ self-sufficiency.

According to the document, while there were some positive outcomes associated with the cash transfer program, such as increased household savings and food security, its overall impact remained limited.

Beneficiary households reported improvements in decision-making autonomy and freedom of movement but failed to see substantial gains in key economic indicators.

The findings come amid ongoing scrutiny of Nigeria’s social intervention programs, with concerns raised about transparency, accountability, and effectiveness.

The cash transfer scheme, once hailed as a critical tool in poverty alleviation, now faces renewed scrutiny as stakeholders call for comprehensive reforms to address its shortcomings.

In response to the World Bank’s report, government officials have emphasized their commitment to enhancing social safety nets and improving the effectiveness of cash transfer programs.

Minister of Finance and Coordinating Minister of the Economy, Wale Edun, reaffirmed the government’s intention to restart social intervention programs soon, following the completion of beneficiary verification processes.

As Nigeria grapples with economic challenges exacerbated by the COVID-19 pandemic and other structural issues, the need for impactful social welfare initiatives has become increasingly urgent.

The World Bank’s assessment underscores the importance of evidence-based policy-making and targeted interventions to address poverty and inequality in the country.

Continue Reading

Economy

DR Congo-China Deal: $324 Million Annually for Infrastructure Hinges on Copper Prices

Published

on

In a significant development for the Democratic Republic of Congo (DRC), a newly revealed contract sheds light on a revamped minerals-for-infrastructure deal with China, signaling billions of dollars in financing contingent upon the price of copper.

This pivotal agreement, signed in March as an extension to a 2008 pact, underscores the intricate interplay between commodity markets and infrastructure development in resource-rich nations.

Under the terms of the updated contract, the DRC stands to receive a substantial injection of $324 million annually for infrastructure projects from its Chinese partners through 2040.

However, there’s a catch: this funding stream is directly linked to the price of copper. As long as the price of copper remains above $8,000 per ton, the DRC is entitled to this considerable sum to bolster its infrastructure.

The latest data indicates that copper is currently trading at $9,910 per ton, well above the threshold specified in the contract.

This bodes well for the DRC’s ambitious infrastructure plans, as the nation seeks to rebuild its road network, which has suffered from decades of neglect and conflict.

However, the contract also outlines a dynamic mechanism that adjusts funding levels based on copper price fluctuations.

Should the price exceed $12,000 per ton, the DRC stands to benefit further, with 30% of the additional profit earmarked for additional infrastructure projects.

Conversely, if copper prices fall below $8,000, the funding will diminish, ceasing altogether if prices dip below $5,200 per ton.

One of the most striking aspects of the contract is the extensive tax exemptions granted to the project, providing a significant financial incentive for both parties involved.

The contract stipulates a total exemption from all indirect or direct taxes, duties, fees, customs, and royalties through the year 2040, further enhancing the attractiveness of the deal for both the DRC and its Chinese partners.

This minerals-for-infrastructure deal, centered around the joint mining venture known as Sicomines, underscores the DRC’s strategic partnership with China, a key player in global commodity markets.

With China Railway Group Ltd., Power Construction Corp. of China (PowerChina), and Zhejiang Huayou Cobalt Co. holding a majority stake in Sicomines, the project represents a significant collaboration between the DRC and Chinese entities.

According to the contract, the total value of infrastructure loans under the deal amounts to a staggering $7 billion between 2008 and 2040, with a substantial portion already disbursed.

This infusion of capital is expected to drive socio-economic development in the DRC, leveraging its vast mineral resources to fund much-needed infrastructure projects.

As the DRC navigates the intricacies of global commodity markets, particularly the volatile copper market, this minerals-for-infrastructure deal with China presents both opportunities and challenges.

While it offers a vital lifeline for infrastructure development, the nation must remain vigilant to ensure that its long-term interests are safeguarded in the face of evolving market dynamics.

Continue Reading

Economy

Fitch Ratings Raises Egypt’s Credit Outlook to Positive Amid $57 Billion Bailout

Published

on

Fitch ratings

Fitch Ratings has upgraded Egypt’s credit outlook to positive, reflecting growing confidence in the North African nation’s economic prospects following an international bailout of $57 billion.

The upgrade comes as Egypt secured a landmark bailout package to bolster its cash-strapped economy and provide much-needed relief amidst economic challenges exacerbated by geopolitical tensions and the global pandemic.

Fitch affirmed Egypt’s credit rating at B-, positioning it six notches below investment grade. However, the shift in outlook to positive shows the country’s progress in addressing external financing risks and implementing crucial economic reforms.

The positive outlook follows Egypt’s recent agreements, including a $35 billion investment deal with the United Arab Emirates as well as additional support from international financial institutions such as the International Monetary Fund and the World Bank.

According to Fitch Ratings, the reduction in near-term external financing risks can be attributed to the significant investment pledges from the UAE, coupled with Egypt’s adoption of a flexible exchange rate regime and the implementation of monetary tightening measures.

These measures have enabled Egypt to navigate its foreign exchange challenges and mitigate the impact of years of managed currency policies.

The recent jumbo interest rate hike has also facilitated the devaluation of the Egyptian pound, addressing one of the country’s most pressing economic issues.

Egypt has faced mounting economic pressures in recent years, including foreign exchange shortages exacerbated by geopolitical tensions in the region.

Challenges such as the Russia-Ukraine conflict and security threats in the Israel-Gaza region have further strained the country’s economic stability.

In response, Egyptian authorities have embarked on a series of reform efforts aimed at enhancing economic resilience and promoting private-sector growth.

These efforts include the sale of state-owned assets, curbing government spending, and reducing the influence of the military in the economy.

While Fitch Ratings’ positive outlook signals confidence in Egypt’s economic trajectory, other rating agencies have also expressed optimism.

S&P Global Ratings has assigned Egypt a B- rating with a positive outlook, while Moody’s Ratings assigns a Caa1 rating with a positive outlook.

Continue Reading
Advertisement




Advertisement
Advertisement
Advertisement

Trending