Connect with us

Energy

FG to Add Additional 817 MWs to The National Grid to Boost Power Supply

The federal government has revealed plans to add an additional 817 megawatts (MWs) of electricity to the national grid to boost power supply within the federal capital territory (FCT) and its environs.

Published

on

ossiomo

The federal government has revealed plans to add an additional 817 megawatts (MWs) of electricity to the national grid to boost power supply within the federal capital territory (FCT) and its environs.

This was disclosed by the Managing Director of Transmission Company of Nigeria (TCN) Mr. Sule Abdulaziz while on a visit to the ongoing projects in the Federal Capital Territory (FCT).

He added that when the project is completed, it would add 1. 465 more transmission lines to the grid, improving and strengthening the FCT’s access to electricity.

In his words, “With the additional lines, TCN capacity of transmission lines will be higher than what is in existence and this means that in future, we can build some sub-stations without upgrading the lines”.

“This is part of efforts to increase transmission wheeling capacity in the FCT and environs. The project is categorized into six lots and is far advanced in execution above 85 percent in total completion by December.

“This will be adequate and it will serve the population of Abuja. The government while making plans for the project has in mind that if the population of FCT increases within five to 10 years, there is a master plan that the station will serve the territory in the next 50 years.

“Construction of complete new 2x60MVA, 132/33 KV substation with 132KV line Bays at Wumba/Lokogoma including about 5km 132 underground XLPE Cable from New Apo Sub Station are ongoing.

“Others are the construction of a 2x150MVA 330/132/33KV substation at New Apo where the managing director frowns at the slow pace of work done by the contractor”.

He also lamented on the recent abysmal supply of electricity, noting that the contracts for all the substations were signed at the same time and wondered why the slow pace of work.

“We have spent a lot of money to clear their containers which entered demurrage and this money is not part of AFD grant but TCN Internally Generated Revenue which could have been used for other projects. We are going to push them to finish the project on time,‘’ he said.

Comments
Advertisement
Advertisement