Economy

Four Power Plants Shut Down in Two Days

Published

on

  • Four Power Plants Shut Down in Two Days

Four of the nation’s power plants shut down this week, making the number of idle plants to rise to nine.

The number of power plants that did not generate any megawatts rose from five on Sunday to eight on Monday and one more shut down on Tuesday, the latest data from the Federal Ministry of Power, Works and Housing showed on Wednesday.

The latest four affected power plants are Sapele I, Alaoji NIPP, Omotosho NIPP and Gbarain NIPP.

Sapele’s ST1 unit was said to be out due to barring gear problem; ST2 out on maintenance; ST4 and 5 awaiting major overhaul, and ST6 tripped on gas control valve not following reference point.

Units GT1 and 2 of Alaoji tripped due to low gas pressure; the GT4 out on maintenance; and the GT3 was shut down due to generator air inlet filter trouble.

Omotosho’s GT1 and four units were out due to gas constraints; GT2 tripped on loss of power supply from the MCC; and the GT3 shut down due to oil leakage on the unit.

Gbarain’s GT2 unit was out on frequency management, report by the ministry showed.

Other idle plants on Tuesday were Afam IV & V, Gbarain II, AES, ASCO and Rivers IPP, according to the latest data from the ministry.

Electricity generation from Egbin, the nation’s biggest power station, stood at 449MW on Tuesday, down from 1,085MW on March 15, 2016. The plant has an installed capacity of 1,320MW, consisting of six units of 220MW each.

The total generation stood at 3,837 megawatts as of 6am on Monday, with seven power plants, including Sapele II and Alaoji II not generating any megawatt.

The power grid has suffered 24 collapses; 15 of which are total and nine, partial, this year.

The nation generates most of its electricity from gas-fired power plants, while output from hydro-power plants makes up about 30 per cent of total generation.

Unutilised generation capacity stood at 2,321.2MW due to gas constraint (1,137.2MW), line constraints (1,034MW) and water management (150MW).

Last month, the Managing Director/Chief Executive Officer, Niger Delta Power Holding Company, Mr. Chiedu Ugbo, said the power plants built under the National Integrated Power Project scheme had suffered from load rejection by Discos.

Meanwhile, the Executive Director, Research and Advocacy, Association of Nigerian Electricity Distributors, Mr. Sunday Oduntan, said on Wednesday that the capacity of the distribution network had increased to 6,200MW.