Fashola Takes Delivery of Abandoned Transmission Equipment

  • Fashola Takes Delivery of Abandoned Transmission Equipment

The Transmission Company of Nigeria has received 77 of its 218 abandoned containers carrying equipment for power transmission projects across the country.

The delivery of the abandoned containers was initiated by the Minister of Power, Works and Housing, Mr. Babatunde Fashola, under the supervision of the Vice President’s Office.

It was gathered that the containers had been abandoned in various ports and terminals across the country for the past eight years.

Speaking on the commencement of the delivery of the abandoned equipment at the Duncan Terminal inside the TinCan Port, Apapa, Lagos, on Wednesday, Fashola said a six-man committee was constituted to initiate the release of the 218 containers.

The minister, who was represented by the Managing Director, TCN, Mr. Abubarka Atiku, said, “A lot of hard work has been put into the negotiations for the release of these consignments due to the accrued demurrage as a result of the suspension of the issuance of import duty exemption certificate for some period in 2014.”

He explained that on the release of the consignments, contractors would move to site immediately to complete ongoing priority and other projects, which would result in improved power supply.

Fashola said, “Some of these projects include the construction of new Abeokuta-Igboora double transmission line and 132kv double-circuit tee-off at Igboora-Igangan; construction of 2x60MVA, 132/33kV substation at Odogunyan and construction of 2x60MVA 132/33kV substation at Ayobo; Ikeja West Ayobo 132kV D/C transmission lines and 2x132kv line bays extension at Ikeja West; construction of Benin North-Osogbo 330KV DC line with turning in and out to the new Akure substation.”

According to him, others include the construction of the Kaduna-Jos 330KV D/C line in Plateau and Kaduna states; installation of 1x60MVA and 132/33kv power transformers, auxiliary equipment and devices at the GCM transmission substation, Onitsha; and construction of 330kv D/C Kaduna Power Plant-Mando substation transmission line.

The Chairman, House of Representatives Committee on Power, Mr. Daniel Asukwo, said the government would release funds to expedite the release of the remaining abandoned containers.

Samed Olukoya

Is the CEO and Founder of Investors King Limited. He is a seasoned foreign exchange research analyst and a published author on Yahoo Finance, Business Insider, Nasdaq, Entrepreneur.com, Investorplace, and other prominent platforms. With over two decades of experience in global financial markets, Olukoya is well-recognized in the industry.

Share
Published by
Samed Olukoya

Recent Posts

Pounds to Naira Black Market Exchange Rate Today, 24th January 2025

The exchange rate between the British Pound (GBP) and the Nigerian Naira (NGN) in the…

6 hours ago

Dollar to Naira Black Market Exchange Rate Today, 24th January 2025

How Much is Dollar to Naira Today in Black Market? As of today, 24th January…

6 hours ago

Tolaram Group Drives Guinness Nigeria to First Profit in Six Months Post-Takeover

Guinness Nigeria Plc has reported a pre-tax profit of N20.1 billion for the second quarter…

11 hours ago

FirstBank’s FirstGem: Redefining Women’s Empowerment in Nigeria

The story of women’s contribution to Nigeria’s economy is as old as the nation itself. …

11 hours ago

UBA to host Knowledge Series Webinar on New Tax Regime for SME’s

Africa’s Global Bank, United Bank for Africa (UBA) Plc, is set to host a Knowledge…

12 hours ago

Moniepoint Partners With Visa to Expand Financial Services for African Businesses

Moniepoint Inc., a leading financial platform in Nigeria, has announced a partnership with Visa, a…

15 hours ago